About this Project
LKB was retained by Suffolk County Department of Public Works to prepare both the preliminary and final design, as well as perform construction support services for the replacement of this concrete bridge which carries Middle Road over Brown’s Creek.
Elements for this project included bridge and diving inspection, coring and material testing, load rating, scour analysis, bridge evaluation, and recommendations. Preliminary and final design included environmental permitting, preliminary and final contract document preparation, and construction support services for the replacement of the bridge with a new longer span concrete arch.
Upon acceptance of the contract documents, LKB provided services during the bidding phase, which included responding to inquiries from prospective bidders; review of contractors’ qualifications and references; preparation of a bid summary; and recommendation of the award to the lowest responsible and qualified bidder. LKB’s construction support services during the construction phase included review and approval of detailed shop drawings, catalog cuts, and miscellaneous submittals for compliance with contract documents; review and responses to RFI’s (Request for Information) and Change Order Requests; and attendance of progress and project meetings, as necessary.
Location
Suffolk County, NY
Client
Suffolk County Department of Public Works
Completion
2014